JFSA provided complete EA documentation, preliminary and final design, and construction administration for the project. We provided the assistant project engineer and several inspectors and testers throughout construction. A particular benefit was derived by assigning our lead designer as the assistant project engineer for the duration of Phase 3. This afforded a unique opportunity to address design-related issues on the spot without the usual delays that can be incurred by going back to the design consultant.

Project Highlights:
US-40/Berthoud Pass US-40/Berthoud Pass East
S-9 (Park Avenue) SH-9 (Park Avenue)
Old Wadsworth Old Wadsworth Big Dry Creek Trail
Martin Luther King Martin Luther King Boulevard Bridge
US-550 US-550 North of Durango (Phase-I)
U-6 at Clear Creek US-6 at Clear Creek and Elk Creek

US-40/Berthoud Pass East

Colorado Department of Transportation Region 1
Clear Creek County, Colorado
US-40/Berthoud Pass

JFSA provided complete EA documentation, preliminary and final design, and construction administration for the project. We provided the assistant project engineer and several inspectors and testers throughout construction. A particular benefit was derived by assigning our lead designer as the assistant project engineer for the duration of Phase 3. This afforded a unique opportunity to address design-related issues on the spot without the usual delays that can be incurred by going back to the design consultant.

Project Highlights:

SH-9 (Park Avenue)

Colorado Department of Transportation Region 1
Breckenridge, Colorado
SH-9

This major reconstruction and widening project at the north end of Breckenridge provided JFSA field staff with numerous administrative and physical challenges. Encompassing more than two construction seasons, JFSA provided the assistant project engineer, as well as inspectors and materials testers. The project included features such as a roundabout, a new bridge over the Blue River, a large stone veneer retaining wall, major utilities, lighting, landscaping, traffic signals, and intersection reconstruction. Due to the recreational character of this main highway in the resort town, maintenance of traffic and public safety and mobility were high priorities.

Project Highlights:

Old Wadsworth Big Dry Creek Trail

City of Westminster
Westminster, Colorado
Old Wadsworth

JFSA provided Construction Management, Inspection and Testing Services for the Local Agency project that consisted of construction of a new 4-lane bridge carrying Old Wadsworth Boulevard over the Big Dry Creek and the Big Dry Creek Open Space Trail for the City of Westminster, Colorado. Major elements include a 2-span, 103-foot long concrete bridge over the creek and trail, rebuilding 1100 feet of Wadsworth Boulevard to a 4-lane arterial cross-section with raised medians and sidewalks, while constructing 2200 feet of 10-foot wide concrete trail. Even though the project was built during the winter months and had major utility work that included coordinating a waterline revision during construction, the project was completed under budget even with these challenges.

Project Highlights:

Martin Luther King Boulevard Bridge

City and County of Denver
Denver, Colorado
Martin Luther King Boulevard Bridge

JFSA provided the project manager and inspector for construction and coordination of a 262-foot two-span steel girder twin structure at the Stapleton redevelopment site. The onsite construction inspector verified that construction activities were in conformance with the plans and specifications. The project manager provided oversight of materials testing to verify that materials such as concrete and soils and all welds conformed with the required specifications. Duties included attending weekly progress meetings, responding to contractor requests for information, and reviewing shop drawings and design changes.

Project Highlights:

US-550 North of Durango (Phase-I)

Colorado Department of Transportation Region 5
Durango, Colorado
US-550

Under an NPS contract with CDOT Region 5, JFSA provided construction inspection services for this 13.5-mile overlay project. The project included shoulder widenings at two major intersections on U-550, as well as installation of 8,237 LF of new guardrail. Coordination of traffic control was a major consideration with the summer tourist traffic, especially during the Iron Horse Bicycle race.

Project Highlights:

US-6 Clear Creek and Elk Creek

Colorado Department of Transportation Region 1
Jefferson County, Colorado
US-6 Clear Creek

To accommodate the politically sensitive corridor of US-6 from Golden to Black Hawk, CDOT undertook the rehabilitation of three bridges to be performed in under 20 calendar days while working around the clock. JFSA provided one of five project engineers and two project inspectors in a partnership with CDOT and three other consulting firms. The project was seen as a highly successful partnership between CDOT, the contractor, and the consulting engineering firms and was completed in only 12 days.